Weathering the Storm

[article]
Preparing for Resource-Constrained Times
Summary:
The economy, like the weather, is a complex system that cycles through good times and bad. Dark economic clouds are brewing on the horizon. Predictions of inflation, stagnant growth, crushing debt, tightening credit are in the forecast. Payson Hall tells us how to weather the storm.

A sea captain needn't be a meteorologist to lead his or her crew through a storm. As a project leader or project manager, you may not be an economist, but you must prepare to deal with the consequences of an economic downturn on your projects.

Some of us (those with grayer hair or grown children) have been through this before. Our experiences with IT projects in the early 80's, early 90's, and 2001-2003 help us know some of what we can expect as the economy slows. History tells us organizations that respond quickly and adeptly are more likely to survive and prosper than those that ignore the problem or deny it until it is too late.

How Will Organizations Respond?

Costs increase. Revenue slows. Profits dwindle. Money available for discretionary spending drops. In the public sector, tax revenues drop, squeezing budgets. Executives in your organization will be under increasing pressure to reduce spending. Some organizations will deal with this more thoughtfully than others.

Inexperienced or poorly managed organizations will implement "across-the-board budget cuts," threatening the viability of mission-critical efforts as well as nice-to-have projects without regard for the risks, rewards, or operational priorities of the organization.

Healthier organizations will review their project portfolios with an eye toward triage, making tough decisions about how increasingly limited resources are allocated:

  • High-risk projects may be canceled if they aren't mission critical, or they may be slowed or delayed to reduce their resource-burn rate.
  • High-cost projects will be reviewed to check their expected return on investment and to confirm they are valuable.
  • Infrastructure projects promising long-term value but near-term disruption may be slowed, paused, or scaled back.
  • Required projects (contractually or legally) that "must be completed" but do not reduce costs or increase revenue in the near term may be reduced to deliver only the essentials of compliance.
  • All projects can expect to have proposed spending and hiring reviewed more critically

What Can You Do To Prepare For The Storm?
Conducting business as usual while watching the storm approach and hoping that it passes without affecting you is foolish and dangerous. A good captain anticipates the weather, and a good project manager anticipates change. Here's a list of activities you should consider to support your organization, your project, and your team:

  1. Review the value your organization expects your project to provide. Significantly lowering costs or increasing revenue is good. Significantly improving products or services to attract new customers or retain existing customers is good. Meeting mandatory contractual or regulatory requirements for survival is good. If your project doesn't meet any of these criteria, its viability is (and should be) suspect. You must understand and be able to explain why your project is important to the organization or be willing to suggest cancellation or delay to support other organizational priorities.
  2. Meet with the project's sponsoring executives individually to candidly discuss their perspective on the six- to eighteen-month forecast for the organization. Do they see organizational priorities changing? Do they anticipate the priority for your project will change? Are some components of your project higher priority to sponsors?
  3. Review requirements for your product or service. Could you partition your project or phase it to accelerate delivery of higher value functions and delay lower value functions? Having such proposals at the ready gives sponsoring executives welcome options.
  4. Review your project's identified risks. An organization's sensitivity to risk often increases in lean economic times. When funding is tight, risks that result in increased costs or delays in realizing a project's value may have a higher impact.
  5. Review your dependencies on external suppliers--some of your suppliers may fail outright,
Tags: 

About the author

Payson Hall's picture Payson Hall

Payson Hall is a consulting project manager for Catalysis Group, Inc. in Sacramento, California. Payson consults on project management issues and teaches project management. Email Payson at payson@catalysisgroup.com. Follow him on twitter at @paysonhall.

AgileConnection is one of the growing communities of the TechWell network.

Featuring fresh, insightful stories, TechWell.com is the place to go for what is happening in software development and delivery.  Join the conversation now!

Upcoming Events

Sep 22
Sep 24
Oct 12
Nov 09